Larsen & Toubro (L&T), the Indian engineering, construction and manufacturing group, reported results for the quarter ended 30 September 2026 (Q2 FY27) on 27 October, after market hours. The headline was a record ₹1.48 lakh crore of new orders in a single quarter, most of it from abroad, along with 33% growth in net profit. Operating margins, however, slipped. Here is what the numbers show, what management said and what to watch next.
Revenue, profit and margins
During the second quarter of fiscal year 2027, the consolidated group registered notable financial progress across key indicators. Consolidated revenue rose 16% to ₹78,750 crore from ₹67,984 crore a year earlier. Net profit grew faster, up 33% to ₹5,202 crore from ₹3,926 crore. BusinessLine reported that lower finance costs, treasury income and better working-capital efficiency helped profit grow ahead of revenue.
Margins moved the other way. The EBITDA margin fell 130 basis points to 8.7% from 10.0%, and EBITDA in rupee terms was largely flat at about ₹6,845 crore. In other words, L&T earned more in total, but less on each rupee of revenue from operations.
Metric (consolidated) | Q2 FY27 | Q2 FY26 | Change |
|---|---|---|---|
Order inflow | ₹1,477 bn | ₹1,158 bn | +28% (quarterly record) |
Revenue | ₹787 bn | ₹680 bn | +16% |
Reported PAT | ₹52 bn | ₹39 bn | +33% |
EBITDA margin | 8.7% | 10.0% | -130 bps |
Order book (30 Sept) | ₹8,535 bn | ₹6,670 bn | +28% |
Source: L&T earnings presentation, 27 October 2026. Figures in ₹ billion as reported by the company; ₹100 bn equals ₹10,000 crore.
Record order inflow, led by international markets
Order inflow was the standout. L&T booked ₹1,477 billion of new orders, which Moneycontrol put at ₹1,47,665 crore. That is 28% more than a year earlier and the company's highest for any quarter.
Most of the new work came from outside India. International orders were ₹924 billion against ₹553 billion from the domestic market; Moneycontrol put the international figure at ₹92,375 crore, about 63% of the quarter's total. BusinessLine reported that more than half of the new orders came from the hydrocarbon and offshore energy business.
The order book, the value of work yet to be executed, stood at ₹8,535 billion (₹8,53,514 crore) on 30 September, up 28% from a year earlier. International projects make up about 54% of it (₹4,623 billion), with domestic projects at ₹3,912 billion.
First-half (H1 FY27) numbers
For April to September 2026, order inflow totalled ₹2,557 billion, 22% more than the ₹2,102 billion booked in the same half a year earlier.
Half-year revenue grew 11% to ₹1,467 billion from ₹1,317 billion, and reported profit rose 24% to ₹93 billion from ₹75 billion. The H1 EBITDA margin was 8.8%, down from 10.0%.
Working capital and cash flow
Net working capital fell to 1.7% of revenue at the end of September 2026 from 10.2% a year earlier, which L&T called a record low. A lower figure means less money is tied up in running projects. Trailing 12-month return on equity was 16.7% against 17.2%; the company said this includes a 100-basis-point hit from a Labour Code provision booked in Q3 FY26.
Cash flow from operations, excluding the financial services business, was ₹128 billion for the quarter against ₹48 billion a year earlier, and ₹180 billion for the half against ₹106 billion.
What management said
In the company's statement, Chairman and MD S N Subrahmanyan said: "This performance reflects continued customer confidence and our ability to secure large and complex orders across sectors and geographies."
R Shankar Raman, president and whole-time director (finance), told BusinessLine that the company sees project prospects worth about ₹10 lakh crore across India and overseas, and that it is optimistic about keeping up its pace of order wins in the second half.
He also flagged a weak spot: about ₹40,000 crore of water supply projects are held up because state governments have been slow to release funds. Deputy Managing Director Subramanian Sarma said the tensions in West Asia had not affected the company's project sites and that its employees were safe, but warned that a prolonged crisis could push some revenue into later periods. The company said revenue and margins could see a lag because of the West Asia situation and higher freight and raw material costs, though it remains confident of protecting them.
What to watch next
Margins: the EBITDA margin fell 130 bps to 8.7%, so investors will look for signs of recovery as new orders are executed.
West Asia: a large share of the order book is international, and management has said a prolonged crisis could delay some revenue.
Water projects: progress on state funding for about ₹40,000 crore of stalled work.
Order momentum: whether the second half keeps up the order-win pace management expects from its roughly ₹10 lakh crore pipeline.
Share price before the results
L&T shares closed 0.4% lower at about ₹3,665 on 27 October 2026, before the results were announced, according to Moneycontrol.
Sources
Larsen & Toubro (Q2 FY27 earnings presentation and results): https://www.larsentoubro.com/
The Hindu BusinessLine: https://www.thehindubusinessline.com/companies/lt-q2-profit-grows-33-to-5202-crore-sees-record-order-intake/article71632610.ece
This article is for information only and is not investment advice.